Planning and material usage
Planning had become a single-expert system. Order data, log inventory, drying schedules and shift notes lived in different places. Planning happened one shift at a time, and every disruption required a manual rebuild.
- Daily plan creation took roughly 2 h 40 min; replanning after a disruption could take 3 h 40 min.
- The planning horizon was effectively one shift, leaving about three viable cutting-pattern choices instead of a 7 to 14 day scenario set.
- Seven unscheduled saw-pattern changes per week created lost time and sequencing instability.
- Kiln fill averaged about 84%, reflecting weak visibility between today's saw schedule and the drying pipeline 5 to 10 days ahead.
- Planning logic lived partly in one technologist's experience; replacing that expertise could take months.